CWPT-LMS
Participant Activity Timeline

   

  May June July August September October November December January February March
National Consultant                     

Site Identified      

X                                                                                      
Conducts Building Orientation           X                                                                            
Attends KC Training Institute                                                                                         
Monitors Progress                               X               X                       X             X  
Shares Findings                                               X       X               X       X        

Site Coordinator

                   
CWPT Acceptance    X X X                                                                                
Attend KC Training Institute           X                                                                            
Conducts Training Component 1 CWPT-LMS                           X X                                                          
Conducts Training Component 2 CWPT Classroom procedure                           X X                                                          
Conducts Training Component 3 Material Preparation                             X X                                                          
Monitors Progress                                 X X X X X X X X X X X X X X     X X X X X X X X X X X X
Data Sharing                                                X       X               X       X